MANILA, Philippines —The Bureau of Internal Revenue (BIR) will conduct a tax fraud audit of contractors flagged for alleged irregularities in flood control projects, its top official said on Tuesday., This news data comes from:http://xthkio.xs888999.com
“Should any contractor be found to have underpaid or evaded taxes, the BIR will not issue an updated tax clearance to them,” Tax Commissioner Romeo Lumagui Jr. said in a statement.
“The contractor will be disqualified from participating in future government procurements, and the final settlement of their existing government contracts will be suspended,” he added.
President Ferdinand Marcos Jr. revealed questionable infrastructure projects, particularly “ghost” flood control works that were reportedly paid for by the government but never constructed.
BIR to audit contractors flagged for ghost flood projects for tax fraud — BIR
Lumagui argued that government contractors are mandated to secure an updated BIR tax clearance before the final settlement of any government project as per the provisions of Revenue Regulation No. 17-2024 (RR No. 17-2024).
“The clearance must certify that the contractor has no outstanding tax liabilities and has duly filed and paid all applicable taxes,” Lumagui said.
“This updated clearance is distinct from the initial tax clearance required during the eligibility phase of the procurement process,” he added.
BIR to audit contractors flagged for ghost flood projects for tax fraud — BIR

- Putin tells Xi China-Russia ties are at 'unprecedented level'
- Thai PM Paetongtarn Shinawatra sacked; new turmoil feared
- Budget shortfall narrows in July
- Fuel prices up for 3rd straight week
- Inoue says taunts 'missed the target' ahead of world title clash
- Four children killed by parents in Dominican Republic — police
- Filipino member of AHOF K-pop group says Manila concert a dream come true
- Sen. Go calls for round-the-clock DFA support for OFWs welfare
- Australia expels Iran ambassador over antisemitic attacks
- COA launches sweeping audit of flood control projects